The headline
The 11.6-kilometre expressway giving direct access between the City of Kigali and the new international airport in Bugesera District is expected to be completed by the end of 2027, the Rwanda Transport Development Agency (RTDA) said, The New Times reported on Monday, November 16, 2026. Grace Nishimwe, Director General of the National Land Authority (NLA), told people buying land along the road that it will have no stopping points and that the land beside it is mainly designated for agriculture.
The details
- The route. The expressway starts where the existing Sonatubes-Gahanga-Akagera four-lane road ends, near the Kanzenze water plant in the Karumuna area, and runs towards the new airport.
- Who it is for. RTDA said the road is meant for airport passengers, tourists, airport staff, cargo operators, logistics companies and other road users. It is designed for faster, smoother travel, with no interruptions from regular traffic, junctions or roadside activities.
- No roadside shops. Nishimwe said some people think they can buy land along the road and set up shops to serve passengers. Under the plan there will be no stopping points, and the land along the road is mainly designated for agriculture. She said people should know such plans before they buy land.
- Wait for the land-use plan. Nishimwe said landowners and buyers along the expressway should wait for the area's land-use plan, expected in December 2026.
- Detailed plans around the airport. Eastern Province Governor Pudence Rubingisa said the government is working with the land authority and Rwanda Airport City management on detailed physical plans for Rilima, Mwogo and Juru, and parts of Mayange and Nyamata sectors. The plans will show how land around the airport should be used.
- The Masaka-Bugesera road. The expressway also links to the 70-kilometre Masaka-Bugesera road, which also connects to the new airport. RTDA said that road is 20 per cent built and will be completed by October 2027. The two are separate but complementary projects, both coordinated by RTDA: the expressway serves the airport's direct access, while the other road strengthens links between the Kigali Logistics Platform and Bugesera.
What it means for property
A plot beside a new expressway is not automatically a commercial plot. If the road has no stopping points and the land along it stays zoned for farming, a roadside shop or petrol station may not be allowed, and paying a commercial price for such land is a risk. If you are looking at land along the airport road, ask the sector what the plot's zone allows today, and wait for the land-use plan NLA expects in December before paying a premium for road frontage.